Determine the total project completion time and the critical path for the project Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity

Question description

McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:

  • Activity 1: Measure office room dimensions
  • Activity 2: Estimate cost
  • Activity 3: Material requisition
  • Activity 4: Workforce requisition
  • Activity 5: Special tool requisition
  • Activity 6: Installation
  • Activity 7: Inspection and customer acceptance

Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

Activities OT MT PT
Activity 1 4 6 14
Activity 2 5 12 16
Activity 3 7 15 23
Activity 4 13 16 28
Activity 5 17 20 35
Activity 6 20 32 50
Activity 7 5 6 13

You must also do the following:

  • Determine the expected completion time and the variance for each activity
  • Determine the total project completion time and the critical path for the project
  • Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
  • What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
  • Define project management and the necessary requirements.
  • Analyze implications of changes in project scheduling.
  • Evaluate application of project management techniques in terms of the firm’s business operational goals and requirements.
find the cost of your paper
Order now to get your homework done

Clarify the role of each legally mandated attendee on the Individualized Education Program team

This discussion assesses your ability to clarify the role of each legally mandated attendee on the Individualized Education Program team. This assessment also supports your achievement of Course Learning Outcome….

Describe the performance of “Salt Peanuts” provided in your Module 3 Playlist

n 100 words or more, describe the performance of “Salt Peanuts” provided in your Module 3 Playlist. Being a live performance, there are certain characteristics that we don’t have in….

Analyze the fixed and variable costs of a firm, how those costs have changed over time, and how those changes have impacted the firm’s overall health and sustainability

The purpose of this milestone is for students to explore the various costs their firm faces and to describe their firm’s market. Using the concepts and tools developed in Modules….