Determine the expected completion time and the variance for each activity

Question description

McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:

  • Activity 1: Measure office room dimensions
  • Activity 2: Estimate cost
  • Activity 3: Material requisition
  • Activity 4: Workforce requisition
  • Activity 5: Special tool requisition
  • Activity 6: Installation
  • Activity 7: Inspection and customer acceptance

Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

Activities OT MT PT
Activity 1 4 6 14
Activity 2 5 12 16
Activity 3 7 15 23
Activity 4 13 16 28
Activity 5 17 20 35
Activity 6 20 32 50
Activity 7 5 6 13

You must also do the following:

  • Determine the expected completion time and the variance for each activity
  • Determine the total project completion time and the critical path for the project
  • Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
  • What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
  • Define project management and the necessary requirements.
  • Analyze implications of changes in project scheduling.
  • Evaluate application of project management techniques in terms of the firm’s business operational goals and requirements.
find the cost of your paper
Order now to get your homework done

How might Rogerian therapy be a helpful strategy for a clients and is it possible these concepts of Rogerian therapy could hinder treatment

Similar to Freud, Carl Rogers developed his theory from his extensive work with his patients. However, unlike Freud, he believed that people are typically healthy; being mentally healthy is the….

Realistically, do you think it is possible to be congruent and to extend empathy and unconditional positive regard to a clients

Similar to Freud, Carl Rogers developed his theory from his extensive work with his patients. However, unlike Freud, he believed that people are typically healthy; being mentally healthy is the….

Analyze two ethical and legal considerations in using standardized interviews or employment tests that assess aptitude, attitude, honesty, and personality during the selection process

Week 4 Discussion 1 “Recruitment Methods” Please respond to the following: Develop a brief plan to recruit for 20 nursing positions for your organization, using both internal and external recruiting….